Repair of tank at Q Block

A.) To supply labour of repair existing HDGP steel tank costs RM3820.00
Comment: Fair enough to any layperson
B.) To supply material of HDPE costs RM3680.00
Comment: sounds OK to any layperson
C.) To supply labour & material of installation works costs RM2800.00
Comment: funny enough. This time labour and material for what then?
D.) To supply labour and material of connect on piping works costs RM7200.00.
Comment: Eh, not again! What type of piping cost so much?
After reading this quotation, I was left in a state of confusion. A number of questions keep circling above my head,"betul-betul pening kepala lo!"
- Why were labour cost quoted over and over, have we (PDPI) being short-changed?
- If so, by whom? The contractor, the Professional management body or our own honourable members?
- Should we report to ACA then?
Sources quoted that this work was carried out under the supervision of our honourable, learned committee member Mr. Chua, who is also a contractor himself. Yes,he may be able to give us a satisfactory explaination.
On the other hand, I am rather uncomfortable with this thought. Morally, this appear to me, a very clear example of conflict of interest. May be the MC members care to explain.
首先我希望读者们能够仔细的审阅这个报价单.这报价单钉在布告栏,有居民/业主向有关方面询问,这个报价单很快的就被下画了.前后只有3-4天吧!奇怪,到底有甚麽蹊跷呢?好吧,让我们逐样逐样的来研究.
A.) 供应劳工于修复现存的HDGP钢大水槽 -- RM3820.00
评论: 对于普通人还蛮公道吧
B.) 供应材料于HDPE -- RM3680.00
评论: 对于普通人还可以接受吧
C.) 供应劳工及材料于安装工程 -- RM2800.00
评论: 奇怪,这次又是甚麽劳工及材料呢?
D.) 供应劳工及材料于衔接配管 --RM7200.00.
评论: 矣,又来一回!甚麽配管这样昂贵的呢?
读后,我也被搞得糊涂啦.满脑的问题.哎!
- 为什么劳工费用一直在重复的.我们(PDPI)是否被蒙了?
- 如是,那又会是给谁蒙了呢?承包商,或是我们专业的管理人或是我们尊敬的管理层委员?
- 是否要呈报贪污局呢?
根据消息,这份工程是由我们尊敬的管理层委员监督的,可能他能够给我们一个很满意的解析.因为他本身也是个承包商.